Project Update: 720 W Bleeker Street – Aspen, CO
Reporting Period: December 2025 / January 2026
Construction activity at 720 W Bleeker Street in Aspen, Colorado began in December 2025 with the project entering its initial demolition phase.
Work Completed in December
Throughout December, construction crews focused on early-stage site preparation activities, including:
Selective demolition of existing site elements
Installation of temporary construction fencing
Implementation of tree protection measures to preserve surrounding landscaping
These activities established a safe and organized jobsite and prepared the property for continued progress.
Current Status
The project is currently in the demolition phase.
Upcoming Work in January
In January, crews will continue demolition-related activities and begin preparing the site for the next phase of construction, pending inspections and approvals.
Community & Safety Commitment
The project team remains committed to minimizing disruption to the surrounding neighborhood while prioritizing safety, site cleanliness, and protection of existing natural features.