Project Update: 720 W Bleeker Street – Aspen, CO

Reporting Period: March 2026 - April 2026

Construction activity at 720 W Bleeker Street progressed steadily throughout March. Key milestones included the installation of new roof trusses, completion of steel structural framing, and installation of new electrical panels.

Work Completed in March

During MArch, crews completed and advanced the following work:

Continued interior framing

Installation of new electrical systems throughout the house

Installation of new roof trusses; roof sheathing completed and prepared for new roofing materials

Installation of new metal structural framing

Installation of a new foundation drainage system

Current Status

The project is currently in Structural Modification Phase.

Upcoming Work in April

Throughout April, crews will:

Completing remaining interior framing

Continuing exterior roofing work

Installing a new gabled roof structure

Advancing general framing activities

Continuing exterior metal framing

Pouring front concrete footings

Community & Site Commitment

The project team will continue maintaining a clean and orderly jobsite, both inside and outside the construction fencing, in an effort to minimize impact to the surrounding neighborhood, including the alleyway and W Bleeker Street.