Project Update: 720 W Bleeker Street – Aspen, CO
Reporting Period: February 2026 - March 2026
Construction activity at 720 W Bleeker Street progressed steadily throughout February, with continued demolition, structural framing, and multiple inspections successfully completed.
Work Completed in February
During February, crews completed and advanced the following work:
Continued exterior and interior demolition
Removal of the existing concrete driveway
Demolition of select interior walls and windows
Began framing new interior walls and window openings on all three floor levels
Installed limited basement plumbing for new drainage systems
Began framing of the new exterior patio on the north side of the residence
Demolished and repoured the garage floor
Pruned multiple trees to maintain optimal tree health and site integrity
Current Status
The project is currently in Structural Modification Phase.
Inspections Passed in February
The following inspections were successfully completed and approved:
Basement slab and window infill inspection
Garage floor rebar and insulation inspection
Lower-level domestic waste plumbing inspection
Tree protection inspection
These approvals confirm compliance with structural, plumbing, and environmental protection requirements and allow the project to advance into the next phase of construction.
Upcoming Work in March
Throughout March, crews will:
Complete remaining limited interior and exterior demolition
Remove the existing roof
Install a new gabled roof structure
Continue framing activities
Community & Site Commitment
The project team will continue maintaining a clean and orderly jobsite, both inside and outside the construction fencing, in an effort to minimize impact to the surrounding neighborhood, including the alleyway and W Bleeker Street.
Project Contact
Patrick McGarry
General Contractor
Aspen Valley Construction
970.989.4504