Project Update: 720 W Bleeker Street – Aspen, CO
Reporting Period: January–February 2026
Construction activity at 720 W Bleeker Street in Aspen, Colorado progressed through January, with continued demolition and early framing work completed.
Work Completed in January
During January, construction crews completed the following activities:
Continued exterior and interior demolition
Interior framing associated with demolition and layout modifications
Installation of mulching for exterior tree root protection
Site preparation for the next phase of framing and structural changes
These efforts helped maintain a safe, organized jobsite while preparing the structure for upcoming construction phases.
Current Status
The project is currently transitioning from demolition into structural modification work.
Upcoming Work in February
Throughout February, crews will continue demolition activities as needed and complete planned framing and structural changes, pending required inspections and approvals.
Community & Safety Commitment
The project team remains committed to minimizing disruption to the surrounding neighborhood while prioritizing safety, site cleanliness, and protection of existing natural features.
Project Contact
Patrick McGarry
General Contractor
Aspen Valley Construction
970.989.4504